Circuito YAMA02
Distribuidora EdeEste - Provincia Monte Plata
| Mes-Año | Jun26 | May26 | Abr26 | Mar26 | Feb26 | Ene26 | Dic25 | Nov25 | Oct25 | Sep25 | Ago25 | Jul25 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Clasificación | A | A | A | A | A | A | A | A | A | A | A | A |
| Clientes | 2437 | 2437 | 2415 | 2429 | 2464 | 2435 | 2407 | 2405 | 3567 | 3350 | 3337 | 3342 |
| % Nivel Cobranza | 0.00% | 88.36% | 92.30% | 106.82% | 93.22% | 101.58% | 109.78% | 97.42% | 92.34% | 98.43% | 79.99% | 102.17% |
| % Nivel Pérdida | 0.00% | 31.20% | 33.66% | 31.37% | 29.17% | 60.15% | 58.44% | 16.24% | 80.44% | 83.30% | 83.16% | 84.22% |
| Energía Suministrada (GWh) | 0 | 0.87 | 0.82 | 0.76 | 0.76 | 1.39 | 1.32 | 0.70 | 4.34 | 4.84 | 5.02 | 4.7 |
| Energía Facturada (GWh) | 0 | 0.60 | 0.54 | 0.52 | 0.54 | 0.55 | 0.55 | 0.58 | 0.85 | 0.81 | 0.85 | 0.74 |
| Energía Cobrada (GWh) | 0 | 0.53 | 0.50 | 0.56 | 0.50 | 0.56 | 0.60 | 0.57 | 0.78 | 0.80 | 0.68 | 0.76 |
| % Servicio | 96.21% | 91.59% | 95.39% | 94.72% | 95.45% | 95.88% | 96.07% | 92.70% | 95.11% | 91.92% | 96.74% | 95.28% |
| % Sin Servicio | 3.79% | 8.41% | 4.61% | 5.28% | 4.55% | 4.12% | 3.93% | 7.30% | 4.89% | 8.08% | 3.26% | 4.72% |
| Interrupción Programada (Hrs) | 42.00 | 48.00 | 36.00 | 42.00 | 42.00 | 34.00 | 20.00 | 36.00 | 37.00 | 31.00 | 12.00 | 14.00 |
| Interrupción Ejecutada (Hrs) | 27.30 | 60.58 | 33.18 | 37.98 | 32.78 | 29.68 | 29.27 | 53.28 | 35.72 | 58.97 | 23.78 | 34.45 |
| Promedio Interrupción Diarias (Hrs) | 0.90 | 1.99 | 1.09 | 1.25 | 1.08 | 0.98 | 0.96 | 1.75 | 1.17 | 1.94 | 0.78 | 1.13 |
| Fecha | Tipo Interrupción | Hora Apertura | Hora Cierre | Duración Total | Causa |
|---|---|---|---|---|---|
| 07/07/2026 | Programada | 10:20:00 | 16:20:00 | 6.00 | DISTRIBUCION (DISPARO/AVERIAS) - LLUVIAS |
| 07/07/2026 | Ejecutada | 16:34:00 | 16:47:00 | 0.22 | DISTRIBUCION (DISPARO/AVERIAS) - LLUVIAS |
| 06/07/2026 | Ejecutada | 18:02:00 | 18:45:00 | 0.72 | DISTRIBUCION (DISPARO/AVERIAS) - CUT OUT ROTO/QUEDAMO/PASADO |
| 05/07/2026 | Ejecutada | 20:55:00 | 21:00:00 | 0.08 | DISTRIBUCION (DISPARO/AVERIAS) - FALLA TRANSITORIA |
| 02/07/2026 | Programada | 09:20:00 | 16:20:00 | 7.00 | DISTRIBUCION (MANTTO. PREV.) - MANTTO. PREV. EN CONDUCTOR // DISTRIBUCION (PROYECTOS) - CONSTRUCCION DE LINEA MT |
| 02/07/2026 | Ejecutada | 11:00:00 | 16:35:00 | 5.97 | DISTRIBUCION (MANTTO. PREV.) - MANTTO. PREV. EN CONDUCTOR // DISTRIBUCION (PROYECTOS) - CONSTRUCCION DE LINEA MT |
| 02/07/2026 | Ejecutada | 00:56:00 | 01:19:00 | 5.97 | DISTRIBUCION (MANTTO. PREV.) - MANTTO. PREV. EN CONDUCTOR // DISTRIBUCION (PROYECTOS) - CONSTRUCCION DE LINEA MT |
| 01/07/2026 | Ejecutada | 20:16:00 | 20:52:00 | 1.28 | DISTRIBUCION (DISPARO/AVERIAS) - RECORRIDO DE LINEA (NO FALLAS) // TRANSMISION - SALIDA DE LINEA 69 KV |
| 01/07/2026 | Ejecutada | 19:13:00 | 19:54:00 | 1.28 | DISTRIBUCION (DISPARO/AVERIAS) - RECORRIDO DE LINEA (NO FALLAS) // TRANSMISION - SALIDA DE LINEA 69 KV |
| 30/06/2026 | Programada | 10:20:00 | 16:20:00 | 6.00 | DISTRIBUCION (PROYECTOS) - CONSTRUCCION DE LINEA MT |
| 30/06/2026 | Ejecutada | 10:55:00 | 16:46:00 | 5.85 | DISTRIBUCION (PROYECTOS) - CONSTRUCCION DE LINEA MT |