Circuito YAGU102E

Distribuidora EdeSur - Provincia San Cristóbal


Mes-Año Abr25 Mar25 Feb25 Ene25 Dic24 Nov24 Oct24 Sep24 Ago24 Jul24 Jun24 May24
Clasificación D D D D D D D D D D D D
Clientes 789 790 790 779 758 654 588 522 519 506 504 504
% Nivel Cobranza 76.83% 83.66% 91.35% 77.23% 84.47% 75.39% 93.00% 94.17% 67.61% 86.39% 93.14% 85.98%
% Nivel Pérdida 82.16% 83.84% 78.64% 78.96% 81.84% 81.54% 84.13% 84.61% 83.00% 86.57% 88.83% 83.52%
Energía Suministrada (GWh) 1.1 1.13 0.92 1 1.04 0.98 1.03 1.06 1.12 1.08 1.06 0.97
Energía Facturada (GWh) 0.2 0.18 0.2 0.21 0.19 0.18 0.16 0.16 0.19 0.14 0.12 0.16
Energía Cobrada (GWh) 0.15 0.15 0.18 0.16 0.16 0.14 0.15 0.15 0.13 0.12 0.11 0.14
% Servicio 97.36% 99.00% 99.90% 99.39% 97.29% 96.96% 97.73% 97.25% 97.37% 96.55% 97.01% 99.05%
% Sin Servicio 2.64% 1.00% 0.10% 0.61% 2.71% 3.04% 2.27% 2.75% 2.63% 3.45% 2.99% 0.95%
Interrupción Programada (Hrs) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.00 0.00
Interrupción Ejecutada (Hrs) 19.27 7.29 0.75 4.47 19.80 22.23 16.57 20.09 19.22 25.21 21.82 6.95
Promedio Interrupción Diarias (Hrs) 0.63 0.24 0.02 0.15 0.65 0.73 0.54 0.66 0.63 0.83 0.72 0.23
Gráfico de Interrupciones

Una semana, a partir de la fecha indicada

Carretera hacia Palenque, Finca de la UNPHU, Carretera Najayo a Boca de Nigua, Los Yagrumos, Najayo Abajo, Palenque, Najayo La Playa.