Circuito UASD103

Distribuidora EdeSur - Provincia Distrito Nacional


Mes-Año Ene26 Dic25 Nov25 Oct25 Sep25 Ago25 Jul25 Jun25 May25 Abr25 Mar25 Feb25
Clasificación C C C C C C C D C C C C
Clientes 2368 2357 2357 2350 2355 2345 2337 2342 2328 2333 2330 2320
% Nivel Cobranza 0.00% 0.00% 98.11% 105.36% 92.73% 95.68% 103.89% 90.81% 191.88% 100.06% 106.26% 100.66%
% Nivel Pérdida 0.00% 0.00% 21.25% 11.21% 5.21% 11.87% 14.62% 4.73% 20.91% -72.03% 11.90% -2.83%
Energía Suministrada (GWh) 0 0 2.51 2.36 2.3 2.36 2.26 2.05 2.12 1.89 3.62 3.2
Energía Facturada (GWh) 0 0 1.98 2.10 2.18 2.08 1.93 1.96 1.68 3.26 3.19 3.29
Energía Cobrada (GWh) 0 0 1.94 2.21 2.02 1.99 2 1.78 3.22 3.26 3.39 3.31
% Servicio 99.99% 99.98% 99.02% 99.92% 100.00% 99.82% 99.99% 99.85% 99.70% 99.41% 99.72% 100.00%
% Sin Servicio 0.01% 0.02% 0.98% 0.08% 0.00% 0.18% 0.01% 0.15% 0.30% 0.59% 0.28% 0.00%
Interrupción Programada (Hrs) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Interrupción Ejecutada (Hrs) 0.04 0.12 7.14 0.56 0.00 1.33 0.06 1.09 2.20 4.30 2.04 0.00
Promedio Interrupción Diarias (Hrs) 0.00 0.00 0.23 0.02 0.00 0.04 0.00 0.04 0.07 0.14 0.07 0.00
Gráfico de Interrupciones

Una semana, a partir de la fecha indicada

Zona Universitaria (Parcial):C/ Robert Schombergk entre la Av. Independencia y George Washington, Av. Independencia desde la Robert Schombergk hasta la Máximo Gómez, Máximo Gómez desde la George Washington hasta casi la Benigno Filomeno De Rojas, Banco Agrícola, Embajada de España, Centro Cuesta Nacional (Máximo Gómez), Av. José Contreras desde la Av. Alma Mater hasta la Av. Máximo Gómez, Av. Santo Tomás de Aquino desde la Av. José Contreras hasta la Av. Independencia, Av. Independencia desde la C/ Santo Tomás de Auino hasta la Av. Máximo Gómez, Av. Bolivar desde la Av. Alma Mater hasta la Av. Máximo Gómez.