Circuito RCL041
Distribuidora EdeEste - Provincia Monte Plata
| Mes-Año | Jul26 | Jun26 | May26 | Abr26 | Mar26 | Feb26 | Ene26 | Dic25 | Nov25 | Oct25 | Sep25 | Ago25 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Clasificación | D | D | D | D | D | D | D | D | D | D | D | D |
| Clientes | 687 | 687 | 686 | 688 | 675 | 647 | 655 | 664 | 679 | 683 | 673 | 685 |
| % Nivel Cobranza | 0.00% | 98.26% | 88.61% | 74.56% | 89.38% | 104.80% | 82.28% | 95.09% | 88.88% | 82.40% | 107.80% | 76.42% |
| % Nivel Pérdida | 0.00% | 73.87% | 70.72% | 65.58% | 68.97% | 71.59% | 65.26% | 72.79% | 77.00% | 75.64% | 68.71% | 64.68% |
| Energía Suministrada (GWh) | 0 | 0.46 | 0.41 | 0.37 | 0.35 | 0.37 | 0.38 | 0.39 | 0.50 | 0.51 | 0.40 | 0.41 |
| Energía Facturada (GWh) | 0 | 0.12 | 0.12 | 0.13 | 0.11 | 0.10 | 0.13 | 0.11 | 0.12 | 0.12 | 0.13 | 0.14 |
| Energía Cobrada (GWh) | 0 | 0.12 | 0.11 | 0.09 | 0.10 | 0.11 | 0.11 | 0.10 | 0.10 | 0.10 | 0.14 | 0.11 |
| % Servicio | 96.73% | 98.52% | 98.03% | 99.21% | 99.16% | 98.25% | 98.61% | 98.73% | 97.82% | 95.84% | 97.61% | 96.15% |
| % Sin Servicio | 3.27% | 1.48% | 1.97% | 0.79% | 0.84% | 1.75% | 1.39% | 1.27% | 2.18% | 4.16% | 2.39% | 3.85% |
| Interrupción Programada (Hrs) | 27.00 | 48.00 | 18.00 | 3.00 | 35.00 | 6.00 | 0.00 | 3.00 | 6.00 | 0.00 | 0.00 | 0.00 |
| Interrupción Ejecutada (Hrs) | 23.57 | 10.68 | 14.15 | 5.72 | 6.08 | 12.57 | 10.03 | 9.43 | 15.92 | 30.35 | 17.42 | 28.08 |
| Promedio Interrupción Diarias (Hrs) | 0.77 | 0.35 | 0.47 | 0.19 | 0.20 | 0.41 | 0.33 | 0.31 | 0.52 | 1.00 | 0.57 | 0.92 |
| Fecha | Tipo Interrupción | Hora Apertura | Hora Cierre | Duración Total | Causa |
|---|---|---|---|---|---|
| 19/08/2026 | Programada | 09:20:00 | 15:20:00 | 6.00 | DISTRIBUCION (MANTTO. PREV.) - MANTTO. PREV. EN CONDUCTOR |
| 19/08/2026 | Ejecutada | 10:41:00 | 11:42:00 | 1.02 | DISTRIBUCION (MANTTO. PREV.) - MANTTO. PREV. EN CONDUCTOR |
| 17/08/2026 | Ejecutada | 09:29:00 | 10:49:00 | 1.75 | DISTRIBUCION (DISPARO/AVERIAS) - SALIDA POR CIRCUITO PADRE // DISTRIBUCION (DISPARO/AVERIAS) - LINEA MT EN EL SUELO |
| 17/08/2026 | Ejecutada | 06:26:00 | 06:51:00 | 1.75 | DISTRIBUCION (DISPARO/AVERIAS) - SALIDA POR CIRCUITO PADRE // DISTRIBUCION (DISPARO/AVERIAS) - LINEA MT EN EL SUELO |
| 15/08/2026 | Ejecutada | 11:09:00 | 11:17:00 | 0.13 | DISTRIBUCION (FACILIDADES OPERATIVAS) - PARA COMPLETAR |
| 13/08/2026 | Ejecutada | 11:22:00 | 11:55:00 | 0.55 | DISTRIBUCION (DISPARO/AVERIAS) - FALLA DE COMUNICACION DEL EQUIPO |
| 12/08/2026 | Programada | 11:20:00 | 17:20:00 | 6.00 | DISTRIBUCION (DISPARO/AVERIAS) - FALLA DE COMUNICACION DEL EQUIPO |
| 12/08/2026 | Ejecutada | 19:18:00 | 19:36:00 | 0.30 | DISTRIBUCION (DISPARO/AVERIAS) - FALLA DE COMUNICACION DEL EQUIPO |