Circuito PALA101

Distribuidora EdeSur - Provincia Santo Domingo


Mes-Año Mar25 Feb25 Ene25 Dic24 Nov24 Oct24 Sep24 Ago24 Jul24 Jun24 May24 Abr24
Clasificación C C A A A A A A A A A A
Clientes 12844 12852 12831 12826 12809 12808 19761 19796 7936 7977 8027 8061
% Nivel Cobranza 102.25% 92.25% 36.74% 112.36% 99.27% 105.10% 69.50% 100.11% 99.47% 91.86% 102.20% 102.91%
% Nivel Pérdida 63.65% 28.16% 37.25% 33.53% 20.20% 62.60% 39.38% 42.32% 38.73% 38.00% 40.20% 35.04%
Energía Suministrada (GWh) 2.76 1.48 1.62 1.76 1.68 3.59 7.85 8.17 7.59 7.54 7.47 6.68
Energía Facturada (GWh) 1 1.07 1.02 1.17 1.34 1.34 4.76 4.71 4.65 4.67 4.47 4.34
Energía Cobrada (GWh) 1.03 0.98 0.37 1.31 1.33 1.41 3.31 4.72 4.63 4.29 4.57 4.47
% Servicio 99.55% 95.97% 92.66% 99.33% 99.61% 98.38% 99.17% 99.18% 98.73% 99.23% 99.85% 99.82%
% Sin Servicio 0.45% 4.03% 7.34% 0.67% 0.39% 1.62% 0.83% 0.82% 1.27% 0.77% 0.15% 0.18%
Interrupción Programada (Hrs) 9.00 18.00 39.00 3.00 0.00 0.00 0.00 3.00 0.00 0.00 0.00 0.00
Interrupción Ejecutada (Hrs) 3.28 29.40 53.58 4.88 2.82 11.83 6.04 5.96 9.30 5.64 1.11 1.29
Promedio Interrupción Diarias (Hrs) 0.11 0.97 1.76 0.16 0.09 0.39 0.20 0.20 0.31 0.19 0.04 0.04
Gráfico de Interrupciones

Una semana, a partir de la fecha indicada

Pantoja (parcial), Villa Morada, Villa del Palmar, Palmarejo, Pantoja (parcial), Villa Flores de Pantoja, Proyecto José Contreras de Pantoja, La Redención de Pantoja, Urb. Villas de Pantoja, La Hondanada, Los Humildes de Pantoja, Planta Tratamiento de la CAASD, Proyecto INVI CEA, Prados de Pantoja, La Redención, Villa El Palmar, Residencial Don Miguel, Carrtera La Isabela (parcial), Residencial Alan, Urb. Don Gregorio I, Don Gregorio III.