| Mes-Año | Jul26 | Jun26 | May26 | Abr26 | Mar26 | Feb26 | Ene26 | Dic25 | Nov25 | Oct25 | Sep25 | Ago25 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Clasificación | D | D | D | D | D | D | D | D | D | D | D | D |
| Clientes | 8034 | 8034 | 8043 | 8050 | 8057 | 8047 | 7762 | 7665 | 7665 | 7622 | 7621 | 7568 |
| % Nivel Cobranza | 0.00% | 79.36% | 93.96% | 88.46% | 87.17% | 87.05% | 81.90% | 100.26% | 94.96% | 96.78% | 84.42% | 84.53% |
| % Nivel Pérdida | 0.00% | 58.71% | 60.65% | 52.60% | 53.19% | 52.16% | 52.74% | 59.92% | 54.97% | 55.16% | 56.18% | 61.32% |
| Energía Suministrada (GWh) | 0 | 5.52 | 5.15 | 4.54 | 4.55 | 4.06 | 4.24 | 4.58 | 4.25 | 4.66 | 5.15 | 5.66 |
| Energía Facturada (GWh) | 0 | 2.28 | 2.03 | 2.15 | 2.13 | 1.94 | 2.00 | 1.84 | 1.91 | 2.09 | 2.25 | 2.19 |
| Energía Cobrada (GWh) | 0 | 1.81 | 1.90 | 1.90 | 1.86 | 1.69 | 1.64 | 1.84 | 1.82 | 2.02 | 1.9 | 1.85 |
| % Servicio | 94.26% | 95.20% | 94.82% | 94.82% | 94.26% | 95.21% | 94.79% | 96.31% | 94.64% | 94.03% | 94.89% | 95.25% |
| % Sin Servicio | 5.74% | 4.80% | 5.18% | 5.18% | 5.74% | 4.79% | 5.21% | 3.69% | 5.36% | 5.97% | 5.11% | 4.75% |
| Interrupción Programada (Hrs) | 22.00 | 23.00 | 23.00 | 23.00 | 28.00 | 22.00 | 22.00 | 17.00 | 22.00 | 26.00 | 18.00 | 7.00 |
| Interrupción Ejecutada (Hrs) | 41.34 | 34.55 | 37.32 | 37.32 | 41.32 | 34.46 | 37.49 | 27.42 | 39.16 | 43.59 | 37.27 | 34.70 |
| Promedio Interrupción Diarias (Hrs) | 1.36 | 1.14 | 1.23 | 1.23 | 1.36 | 1.13 | 1.23 | 0.90 | 1.29 | 1.43 | 1.23 | 1.14 |
| Fecha | Tipo Interrupción | Hora Apertura | Hora Cierre | Duración Total | Causa |
|---|---|---|---|---|---|
| 20/08/2026 | Programada | 09:00:00 | 14:00:00 | 5.00 | DIVERSAS INTERVENCIONES EN LA RED // FALLA TRANSITORIA // |
| 20/08/2026 | Ejecutada | 21:05:59 | 21:10:48 | 6.11 | DIVERSAS INTERVENCIONES EN LA RED // FALLA TRANSITORIA // |
| 20/08/2026 | Ejecutada | 09:00:33 | 15:02:24 | 6.11 | DIVERSAS INTERVENCIONES EN LA RED // FALLA TRANSITORIA // |
| 19/08/2026 | Ejecutada | 20:36:38 | 20:38:10 | 0.03 | FALLA TRANSITORIA // |
| 18/08/2026 | Programada | 16:00:00 | 18:00:00 | 2.00 | EN MANTENIMIENTO // |
| 18/08/2026 | Ejecutada | 16:13:13 | 18:59:02 | 2.76 | EN MANTENIMIENTO // |
| 16/08/2026 | Ejecutada | 21:07:31 | 21:10:06 | 0.12 | FALLA TRANSITORIA // FALLA TRANSITORIA // FALLA TRANSITORIA |
| 16/08/2026 | Ejecutada | 12:04:23 | 12:06:28 | 0.12 | FALLA TRANSITORIA // FALLA TRANSITORIA // FALLA TRANSITORIA |
| 16/08/2026 | Ejecutada | 08:27:25 | 08:30:05 | 0.12 | FALLA TRANSITORIA // FALLA TRANSITORIA // FALLA TRANSITORIA |
| 15/08/2026 | Ejecutada | 20:48:42 | 21:05:28 | 3.24 | DISPARO LÍNEA 69 KV // DISPARO LÍNEA 69 KV // DISPARO LÍNEA 69 KV |
| 15/08/2026 | Ejecutada | 18:02:44 | 20:47:09 | 3.24 | DISPARO LÍNEA 69 KV // DISPARO LÍNEA 69 KV // DISPARO LÍNEA 69 KV |
| 15/08/2026 | Ejecutada | 16:45:45 | 16:58:51 | 3.24 | DISPARO LÍNEA 69 KV // DISPARO LÍNEA 69 KV // DISPARO LÍNEA 69 KV |
| 14/08/2026 | Ejecutada | 19:49:23 | 20:26:05 | 2.12 | DETERIORO // CORRECTIVO EN CONDUCTOR DE TIERRA // DETERIORO |
| 14/08/2026 | Ejecutada | 19:47:05 | 19:49:19 | 2.12 | DETERIORO // CORRECTIVO EN CONDUCTOR DE TIERRA // DETERIORO |
| 14/08/2026 | Ejecutada | 17:56:14 | 18:34:27 | 2.12 | DETERIORO // CORRECTIVO EN CONDUCTOR DE TIERRA // DETERIORO |
| 14/08/2026 | Ejecutada | 10:42:09 | 11:32:28 | 2.12 | DETERIORO // CORRECTIVO EN CONDUCTOR DE TIERRA // DETERIORO |
| 13/08/2026 | Programada | 09:00:00 | 14:00:00 | 5.00 | DIVERSAS INTERVENCIONES EN LA RED // |
| 13/08/2026 | Ejecutada | 09:05:39 | 15:14:30 | 6.15 | DIVERSAS INTERVENCIONES EN LA RED // |