Circuito MVIE104

Distribuidora EdeSur - Provincia San Cristóbal


Mes-Año Jul25 Jun25 May25 Abr25 Mar25 Feb25 Ene25 Dic24 Nov24 Oct24 Sep24 Ago24
Clasificación B A A B B B A A A A A A
Clientes 3786 3786 3782 3765 3756 3765 3770 3777 3791 3788 3766 3756
% Nivel Cobranza 0.00% 84.92% 105.23% 89.43% 104.24% 94.34% 102.84% 111.99% 96.77% 106.76% 82.73% 100.74%
% Nivel Pérdida 0.00% 20.96% 29.87% 17.81% 31.23% 15.24% 20.84% 25.11% 8.70% 24.81% 21.26% 25.26%
Energía Suministrada (GWh) 0 2.48 2.5 2.2 2.34 1.95 2.17 2.3 2.13 2.69 2.59 2.71
Energía Facturada (GWh) 0 1.96 1.76 1.81 1.61 1.65 1.72 1.72 1.94 2.03 2.04 2.03
Energía Cobrada (GWh) 0 1.66 1.85 1.62 1.68 1.56 1.77 1.93 1.88 2.16 1.69 2.04
% Servicio 97.89% 98.68% 98.68% 97.62% 98.16% 98.72% 99.26% 99.39% 96.97% 98.95% 98.44% 97.88%
% Sin Servicio 2.11% 1.32% 1.32% 2.38% 1.84% 1.28% 0.74% 0.61% 3.03% 1.05% 1.56% 2.12%
Interrupción Programada (Hrs) 7.00 5.00 11.00 13.00 8.00 0.00 1.00 1.00 2.00 1.00 3.00 0.00
Interrupción Ejecutada (Hrs) 15.40 9.63 9.67 17.38 13.45 9.35 5.37 4.43 22.11 7.65 11.38 15.47
Promedio Interrupción Diarias (Hrs) 0.51 0.32 0.32 0.57 0.44 0.31 0.18 0.15 0.73 0.25 0.37 0.51
Gráfico de Interrupciones

Una semana, a partir de la fecha indicada

Centro del Pueblo de San Cristóbal (parcial), Lavapiés (parcial), Grupo Ramos (San Cristóbal), Pueblo Nuevo, Carretera Sánchez Vieja, San Isidro.