Circuito KQAZ101

Distribuidora EdeSur - Provincia Azua


Mes-Año Abr25 Mar25 Feb25 Ene25 Dic24 Nov24 Oct24 Sep24 Ago24 Jul24 Jun24 May24
Clasificación D D D A A A A A A A A A
Clientes 1490 1489 1498 1502 1493 1512 1515 1521 1524 1521 1525 1514
% Nivel Cobranza 91.79% 85.09% 81.55% 83.87% 110.03% 96.58% 84.32% 76.78% 90.67% 83.90% 97.46% 100.20%
% Nivel Pérdida 55.19% 61.26% 54.40% 60.17% 65.05% 56.41% 62.64% 68.63% 67.72% 64.01% 68.95% 65.71%
Energía Suministrada (GWh) 1.97 2.19 1.69 1.78 1.86 1.69 2.22 2.36 2.19 1.92 1.98 1.96
Energía Facturada (GWh) 0.88 0.85 0.77 0.71 0.65 0.74 0.83 0.74 0.71 0.69 0.61 0.67
Energía Cobrada (GWh) 0.81 0.72 0.63 0.59 0.72 0.71 0.7 0.57 0.64 0.58 0.6 0.67
% Servicio 98.44% 98.44% 96.39% 92.15% 99.97% 98.21% 98.96% 98.87% 99.21% 98.02% 98.93% 98.49%
% Sin Servicio 1.56% 1.56% 3.61% 7.85% 0.03% 1.79% 1.04% 1.13% 0.79% 1.98% 1.07% 1.51%
Interrupción Programada (Hrs) 6.00 3.00 18.00 40.00 0.00 6.00 0.00 3.00 3.00 0.00 0.00 0.00
Interrupción Ejecutada (Hrs) 11.37 11.42 26.36 57.33 0.19 13.10 7.61 8.28 5.77 14.45 7.81 11.00
Promedio Interrupción Diarias (Hrs) 0.37 0.38 0.87 1.88 0.01 0.43 0.25 0.27 0.19 0.48 0.26 0.36
Gráfico de Interrupciones

Una semana, a partir de la fecha indicada

La Fortaleza del Kilometro 15 de Azua, Proyecto Ysura, Teleantilla, Los Negros, El Rosario, La Ciénaga, Nuevo Curro, Proyecto Ganadero, Barrera.