Circuito JUCO101B

Distribuidora EdeSur - Provincia Pedernales


Mes-Año Abr25 Mar25 Feb25 Ene25 Dic24 Nov24 Oct24 Sep24 Ago24 Jul24 Jun24 May24
Clasificación D D D D A D D A D D D D
Clientes 2116 2116 2122 2119 2109 2132 2150 2151 2138 2139 2139 2118
% Nivel Cobranza 0.00% 85.03% 76.53% 76.75% 75.03% 77.08% 92.26% 77.52% 74.68% 73.36% 72.53% 78.78%
% Nivel Pérdida 0.00% 72.62% 66.77% 69.66% 72.81% 65.32% 69.74% 65.88% 66.50% 65.98% 65.96% 65.39%
Energía Suministrada (GWh) 0 1.28 1.13 1.29 1.35 1.05 1.13 1.16 1.23 1.18 1.15 1.08
Energía Facturada (GWh) 0 0.35 0.38 0.39 0.37 0.36 0.34 0.4 0.41 0.4 0.39 0.37
Energía Cobrada (GWh) 0 0.3 0.29 0.3 0.28 0.28 0.32 0.31 0.31 0.29 0.28 0.29
% Servicio 98.12% 99.09% 97.83% 98.62% 97.95% 96.75% 96.80% 97.19% 96.54% 96.06% 96.90% 97.53%
% Sin Servicio 1.88% 0.91% 2.17% 1.38% 2.05% 3.25% 3.20% 2.81% 3.46% 3.94% 3.10% 2.47%
Interrupción Programada (Hrs) 0.00 0.00 0.00 4.00 3.00 6.00 3.00 0.00 0.00 12.00 8.00 4.00
Interrupción Ejecutada (Hrs) 13.71 6.66 15.82 10.07 14.96 23.74 23.37 20.55 25.23 28.78 22.62 18.02
Promedio Interrupción Diarias (Hrs) 0.45 0.22 0.52 0.33 0.49 0.78 0.77 0.68 0.83 0.95 0.74 0.59
Gráfico de Interrupciones

Una semana, a partir de la fecha indicada

Ojeda, Los Patos, Los Blancos, Caletón, Las Merceditas, Paraíso, San Rafael.