Mes-Año | Abr25 | Mar25 | Feb25 | Ene25 | Dic24 | Nov24 | Oct24 | Sep24 | Ago24 | Jul24 | Jun24 | May24 |
---|---|---|---|---|---|---|---|---|---|---|---|---|
Clasificación | B | B | B | B | B | B | B | B | B | B | A | B |
Clientes | 15920 | 15920 | 15869 | 9951 | 15364 | 15364 | 15354 | 15358 | 15321 | 15244 | 0 | 15088 |
% Nivel Cobranza | 0.00% | 103.55% | 91.76% | 97.67% | 105.77% | 2.03% | 106.74% | 91.03% | 93.83% | 100.31% | 89.00% | 97.29% |
% Nivel Pérdida | 0.00% | 21.49% | 12.10% | 22.19% | 26.40% | 8.40% | 17.64% | 9.94% | 20.63% | 18.78% | 16.86% | 21.23% |
Energía Suministrada (GWh) | 0 | 3.94 | 3.48 | 4.01 | 4.1 | 3.45 | 3.96 | 3.8 | 4.26 | 3.97 | 3.63 | 3.62 |
Energía Facturada (GWh) | 0 | 3.09 | 3.06 | 3.12 | 3.02 | 3.16 | 3.26 | 3.43 | 3.38 | 3.23 | 3.02 | 2.85 |
Energía Cobrada (GWh) | 0 | 3.2 | 2.8 | 3.05 | 3.19 | 0.06 | 3.48 | 3.12 | 3.17 | 3.24 | 2.69 | 2.78 |
% Servicio | 97.33% | 99.00% | 99.86% | 99.92% | 99.86% | 98.77% | 98.72% | 98.65% | 99.42% | 97.37% | 0.00% | 98.73% |
% Sin Servicio | 2.67% | 1.00% | 0.14% | 0.08% | 0.14% | 1.23% | 1.28% | 1.35% | 0.58% | 2.63% | 0.00% | 1.27% |
Interrupción Programada (Hrs) | 38.00 | 18.00 | 0.00 | 0.00 | 7.00 | 7.00 | 4.00 | 5.00 | 10.00 | 6.00 | 0.00 | 5.00 |
Interrupción Ejecutada (Hrs) | 19.51 | 7.30 | 0.99 | 0.60 | 1.03 | 9.01 | 9.36 | 9.83 | 4.22 | 19.22 | 0.00 | 9.24 |
Promedio Interrupción Diarias (Hrs) | 0.64 | 0.24 | 0.03 | 0.02 | 0.03 | 0.30 | 0.31 | 0.32 | 0.14 | 0.63 | 0.00 | 0.30 |
El Salto (Pedregal), Pedregal, Larga (Pedregal), Proyecto Yerba Buena, Salto Baiguate, Sabaneta, Carretera Al Rancho, Carretera La Joya, Carretera Al Rancho Baiguate, Urb. El Dorado Parcial, Pinar Dorado, Avenida Victor Capellan, Hamaca de Dios, Palo Blanco Parcial, Colonia Japonesa, Urb. Medina 2, Don Bosco, Centro del Pueblo parcial, Gaston F. Deligne.