Circuito INVI04
Distribuidora EdeEste - Provincia Santo Domingo
| Mes-Año | Sep26 | Ago26 | Jul26 | Jun26 | May26 | Abr26 | Mar26 | Feb26 | Ene26 | Dic25 | Nov25 | Oct25 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Clasificación | A | A | A | A | A | A | A | A | A | A | A | A |
| Clientes | 8385 | 8379 | 8366 | 8366 | 8345 | 8329 | 8304 | 8360 | 8322 | 8240 | 8227 | 8226 |
| % Nivel Cobranza | 93.86% | 93.20% | 99.91% | 94.44% | 84.70% | 96.07% | 102.24% | 91.50% | 103.91% | 100.44% | 111.02% | 109.69% |
| % Nivel Pérdida | 28.09% | 31.20% | 33.91% | 33.64% | 32.16% | 17.70% | 30.73% | 22.38% | 30.26% | 30.81% | 30.14% | 30.98% |
| Energía Suministrada (GWh) | 6.44 | 6.71 | 6.64 | 6.21 | 5.78 | 5.11 | 4.80 | 4.37 | 4.8 | 5.29 | 5.38 | 6.09 |
| Energía Facturada (GWh) | 4.63 | 4.62 | 4.39 | 4.12 | 3.92 | 4.21 | 3.32 | 3.39 | 3.35 | 3.66 | 3.76 | 4.2 |
| Energía Cobrada (GWh) | 4.34 | 4.30 | 4.38 | 3.89 | 3.32 | 4.04 | 3.40 | 3.10 | 3.48 | 3.67 | 4.17 | 4.61 |
| % Servicio | 98.51% | 99.09% | 99.97% | 97.09% | 96.69% | 98.98% | 99.46% | 98.55% | 98.31% | 99.29% | 98.03% | 98.41% |
| % Sin Servicio | 1.49% | 0.91% | 0.03% | 2.91% | 3.31% | 1.02% | 0.54% | 1.45% | 1.69% | 0.71% | 1.97% | 1.59% |
| Interrupción Programada (Hrs) | 0.00 | 6.00 | 3.00 | 0.00 | 20.00 | 0.00 | 6.00 | 0.00 | 9.00 | 3.00 | 4.00 | 0.00 |
| Interrupción Ejecutada (Hrs) | 10.75 | 6.57 | 0.18 | 20.97 | 23.82 | 7.35 | 3.92 | 10.43 | 12.18 | 5.28 | 14.42 | 11.63 |
| Promedio Interrupción Diarias (Hrs) | 0.35 | 0.22 | 0.01 | 0.69 | 0.78 | 0.24 | 0.13 | 0.34 | 0.40 | 0.17 | 0.47 | 0.38 |
| Fecha | Tipo Interrupción | Hora Apertura | Hora Cierre | Duración Total | Causa |
|---|---|---|---|---|---|
| 20/10/2026 | Ejecutada | 11:04:00 | 12:32:00 | 1.47 | SS/EE (MATTO. PREV.) - MATTO. GENERAL Y ENSAYO EQUIPOS E INTERRUPTORES |
| 16/10/2026 | Programada | 09:20:00 | 12:20:00 | 3.00 | MEDICIÓN MT - TRANSFORMADOR DE CORRIENTE // DISTRIBUCION (DISPARO/AVERIAS) - FALLOS EN CONDUCTOR |
| 16/10/2026 | Ejecutada | 19:22:00 | 19:33:00 | 0.38 | MEDICIÓN MT - TRANSFORMADOR DE CORRIENTE // DISTRIBUCION (DISPARO/AVERIAS) - FALLOS EN CONDUCTOR |
| 16/10/2026 | Ejecutada | 10:20:00 | 10:32:00 | 0.38 | MEDICIÓN MT - TRANSFORMADOR DE CORRIENTE // DISTRIBUCION (DISPARO/AVERIAS) - FALLOS EN CONDUCTOR |
| 15/10/2026 | Ejecutada | 21:29:00 | 21:35:00 | 0.10 | DISTRIBUCION (DISPARO/AVERIAS) - JUMPER MT ABIERTO |
| 13/10/2026 | Programada | 09:20:00 | 17:20:00 | 8.00 | DISTRIBUCION (PROYECTOS) - INTERCONEXION DE PROYECTO MT // OTRA EMPRESA DE DISTRIBUCION - FACILITAR TRABAJOS MINISTERIO DE ENERGIA Y MINAS // DISTRIBUCION (DISPARO/AVERIAS) - FALLA DE COMUNICACION DEL EQUIPO |
| 13/10/2026 | Ejecutada | 23:16:00 | 23:25:00 | 7.45 | DISTRIBUCION (PROYECTOS) - INTERCONEXION DE PROYECTO MT // OTRA EMPRESA DE DISTRIBUCION - FACILITAR TRABAJOS MINISTERIO DE ENERGIA Y MINAS // DISTRIBUCION (DISPARO/AVERIAS) - FALLA DE COMUNICACION DEL EQUIPO |
| 13/10/2026 | Ejecutada | 12:46:00 | 17:15:00 | 7.45 | DISTRIBUCION (PROYECTOS) - INTERCONEXION DE PROYECTO MT // OTRA EMPRESA DE DISTRIBUCION - FACILITAR TRABAJOS MINISTERIO DE ENERGIA Y MINAS // DISTRIBUCION (DISPARO/AVERIAS) - FALLA DE COMUNICACION DEL EQUIPO |
| 13/10/2026 | Ejecutada | 09:55:00 | 12:44:00 | 7.45 | DISTRIBUCION (PROYECTOS) - INTERCONEXION DE PROYECTO MT // OTRA EMPRESA DE DISTRIBUCION - FACILITAR TRABAJOS MINISTERIO DE ENERGIA Y MINAS // DISTRIBUCION (DISPARO/AVERIAS) - FALLA DE COMUNICACION DEL EQUIPO |