Circuito CORD401

Distribuidora EdeNorte - Provincia Monseñor Nouel


Mes-Año Ago17 Jul17 Jun17 May17 Abr17 Mar17 Feb17 Ene17 Dic16 Nov16 Oct16 Sep16
Clasificación A A A A A A A A A A A A
Clientes 1 1 1 1 1 1 1 1 1 1 1 1
% Nivel Cobranza 0.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
% Nivel Pérdida 0.00% -2.89% 3.07% 9.77% -8.12% 12.09% -19.51% -0.26% 2.30% 0.14% -1.01% -4.94%
Energía Suministrada (GWh) 0 1.62 1.67 1.62 1.46 1.58 1.39 1.66 1.66 1.63 16.24 1.64
Energía Facturada (GWh) 0 1.67 1.62 1.46 1.58 1.39 1.66 1.66 1.63 1.62 16.4 1.72
Energía Cobrada (GWh) 0 1.67 1.62 1.46 1.58 1.39 1.66 1.66 1.63 1.62 16.4 1.72
% Servicio 99.11% 99.77% 99.16% 99.11% 96.89% 99.21% 99.75% 100.00% 99.61% 97.68% 99.00% 99.07%
% Sin Servicio 0.89% 0.23% 0.84% 0.89% 3.11% 0.79% 0.25% 0.00% 0.39% 2.32% 1.00% 0.93%
Interrupción Programada (Hrs) 0.00 6.00 0.00 0.00 24.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Interrupción Ejecutada (Hrs) 6.48 1.68 6.17 6.50 22.70 5.73 1.80 0.00 2.87 16.92 7.33 6.77
Promedio Interrupción Diarias (Hrs) 0.21 0.06 0.20 0.21 0.75 0.19 0.06 0.00 0.09 0.56 0.24 0.22
Gráfico de Interrupciones

Una semana, a partir de la fecha indicada

Reporte de Ejecución - Circuito CORD401
Interrupciones Programadas 6
Interrupciones Ejecutadas 6.15
% Ejecución Operativa 102.50%
Detalle de Salidas - Circuito CORD401
Fecha Tipo Interrupción Hora Apertura Hora Cierre Duración Total Causa
02/08/2017 Programada 09:00:00 15:00:00 6
02/08/2017 Ejecutada 09:40:00 15:49:00 6.15 APERTURA DE LINEA DE TRANSMISION
Cormidon