Circuito CABA102
Distribuidora EdeSur - Provincia Santo Domingo
| Mes-Año | Jul26 | Jun26 | May26 | Abr26 | Mar26 | Feb26 | Ene26 | Dic25 | Nov25 | Oct25 | Sep25 | Ago25 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Clasificación | A | A | A | A | A | A | A | A | A | A | A | A |
| Clientes | 836 | 836 | 757 | 744 | 735 | 750 | 941 | 938 | 938 | 949 | 22 | 23 |
| % Nivel Cobranza | 0.00% | 88.11% | 88.21% | 81.77% | 132.29% | 123.64% | 73.66% | 103.00% | 86.44% | 108.64% | 98.21% | 94.06% |
| % Nivel Pérdida | 0.00% | 48.17% | 51.32% | 51.75% | 49.85% | 34.86% | 24.89% | 21.67% | 41.26% | 35.56% | 27.29% | 39.13% |
| Energía Suministrada (GWh) | 0 | 2.43 | 1.63 | 1.48 | 1.53 | 1.38 | 1.57 | 2.57 | 2.67 | 1.95 | 1.61 | 1.71 |
| Energía Facturada (GWh) | 0 | 1.26 | 0.79 | 0.72 | 0.77 | 0.90 | 1.18 | 2.01 | 1.57 | 1.26 | 1.17 | 1.04 |
| Energía Cobrada (GWh) | 0 | 1.11 | 0.70 | 0.58 | 1.02 | 1.11 | 0.87 | 2.07 | 1.36 | 1.37 | 1.15 | 0.98 |
| % Servicio | 97.34% | 97.89% | 98.44% | 98.44% | 99.26% | 98.31% | 99.12% | 99.03% | 97.89% | 98.16% | 100.00% | 99.59% |
| % Sin Servicio | 2.66% | 2.11% | 1.56% | 1.56% | 0.74% | 1.69% | 0.88% | 0.97% | 2.11% | 1.84% | 0.00% | 0.41% |
| Interrupción Programada (Hrs) | 6.00 | 1.00 | 3.00 | 3.00 | 1.00 | 1.00 | 0.00 | 0.00 | 0.00 | 6.00 | 0.00 | 0.00 |
| Interrupción Ejecutada (Hrs) | 19.17 | 15.19 | 11.25 | 11.25 | 5.36 | 12.18 | 6.32 | 7.21 | 15.43 | 13.42 | 0.00 | 2.99 |
| Promedio Interrupción Diarias (Hrs) | 0.63 | 0.50 | 0.37 | 0.37 | 0.18 | 0.40 | 0.21 | 0.24 | 0.51 | 0.44 | 0.00 | 0.10 |
| Fecha | Tipo Interrupción | Hora Apertura | Hora Cierre | Duración Total | Causa |
|---|---|---|---|---|---|
| 14/08/2026 | Ejecutada | 15:36:21 | 15:40:26 | 0.07 | FALLA TRANSITORIA // |
| 12/08/2026 | Ejecutada | 15:29:31 | 15:40:27 | 0.18 | DISPARO LÍNEA 69 KV // |
| 11/08/2026 | Ejecutada | 08:38:35 | 08:41:08 | 0.04 | FALLA TRANSITORIA // |
| 08/08/2026 | Ejecutada | 21:27:28 | 21:31:32 | 0.29 | DISPARO LÍNEA 69 KV // FALLA TRANSITORIA // |
| 08/08/2026 | Ejecutada | 15:36:55 | 15:50:29 | 0.29 | DISPARO LÍNEA 69 KV // FALLA TRANSITORIA // |
| 07/08/2026 | Ejecutada | 07:04:37 | 07:07:17 | 0.04 | FALLA TRANSITORIA // |